| 18 | === Project Goals and Timeline === |
| 19 | |
| 20 | ||= Due Date =||= SMART goal =||= Measure =||= Status =|| |
| 21 | ||||||'''First trimester (17 May - 05 August)'''|| |
| 22 | || 30 May || Retrieve list of active modules and mark them selected by default || List was correctly retrieved || Completed || |
| 23 | || 15 June || Display only active modules along with name_nice || Core modules and others were hidden correctly || Completed || |
| 24 | || 24 June || Build a dependency system for selection of modules || Was done correctly for inv module and tested (When only inv was selected strings from supply were also displayed || Completed |
| 25 | || 5th July || Retrieve list of csv files from tasks.cfg file inside template folder || Using S3BulkImported Class || Ongoing |